Obtain the data you need to make the most informed decisions by accessing our extensive portfolio of information, analytics, and expertise. Sign in to the product or service center of your choice.
A clearer path to the UK's ambitious 50 GW of offshore wind by
2030 goal emerged in recent days as National Grid ESO laid out what
it sees as the optimal transmission requirements and nearly 7 GW of
projects won financial backing from the Department for Business,
Energy & Industrial Strategy (BEIS).
British electricity system operator National Grid ESO's "Pathway to 2030 Holistic Network
Design" (HND) would link 23 GW of projects with each other and
demand centers, partly through hubs, in the first step away from
the radial transmission design that until now underpinned the UK's
reign as the top-ranked nation in Europe for offshore wind
installation at 12.2 GW currently.
BEIS, meanwhile, offered guaranteed prices known as Contracts
for Difference (CfD) that will allow a slew of offshore wind
projects to proceed knowing returns are locked in. Alongside
offshore wind projects, BEIS also awarded support to onshore wind,
solar, and tidal project developers in Allocation Round 4 (AR4). In
total, almost 11 GW of facilities won support on 7 July.
How to connect the offshore wind farms on the horizon will be
key. The HND defines a network topology (see map below),
capacities, and interface sites. It provides connection
recommendations for 23 GW of offshore wind and the associated
transmission network to get the power produced to where it is
needed.
S&P Global Commodity Insights Senior Research Analyst Diego
Ortiz Garcia told Net-Zero Business Daily what struck him
about the plan was that it was a cost efficient path to developing
the offshore areas needed to make a stab at getting to 50 GW.
Source: National Grid ESO
The HND design would connect all 18 "in scope offshore wind
farms" to the onshore network, has 15 landing points, and would
lead to 10 new 525-kV high voltage direct current (HVDC) circuits
with appropriate converter stations, offshore substations, and
cables, National Grid ESO said.
When all those projects are added up, the cost of the offshore
network infrastructure required in the recommended design would be
£32 billion ($38.1 billion), compared with £24.4 billion for an
optimized radial design, it said. The cost of the related onshore
network infrastructure would be £21.7 billion, it added.
National Grid ESO said its recommended path offers overall net
consumer savings of about £5.5 billion. The design leads to an
extra £7.6 billion in capital costs due to additional offshore
infrastructure, but this is outweighed by £13.1 billion in
constraint cost savings compared with a radial design, it said.
In addition, the plan could create up to 168,000 jobs by 2030,
reduce the cable impact on the seabed by up to 30%, and reduce CO2
emissions by 2 mega metric tons between 2030 and 2032, it said.
Tom Thackray, Confederation of British Industry decarbonization
program director, told Net-Zero Business Daily on 12 July,
the plans "will support a modern and flexible energy system and
ensure all parts of the UK can benefit," but "to enable this vision
it is essential that planning and consenting regimes are
streamlined to enable the swift roll out of the infrastructure this
decade."
HND includes offshore wind projects that secured seabed leases
through The Crown Estate's Offshore Wind Leasing Round 4
and Crown Estate Scotland's ScotWind Leasing Round. It also
assumes 1 GW of floating wind will be built following a 2023 Celtic
Sea leasing round.
On 5 July, the Crown Estate, which oversees government lands in
England, Wales and Northern Ireland, advanced those Celtic Sea
efforts, announcing the areas expected
to be part of the "mid-2023" auction. It expects the areas to
deliver 4 GW of floating offshore wind by 2035. HVDC is a much
better option for floating offshore wind because the sites tend to
be further from the shore, Ortiz Garcia noted.
Grid expansion backing
All three UK electricity transmission owners—National Grid
Electricity Transmission, SSEN Transmission, and SP
Transmission—welcomed the HND plan, arguing "a subsea
superhighway" was now in the works.
SSEN Transmission Managing Director Rob McDonald said the plans
were a "huge step forward" for the UK's energy security and an
electricity system independent of imported gas. He added that "this
blueprint can unlock Scotland's vast offshore wind resources."
Until now, the UK's offshore wind fleet has connected to shore
using a "radial" model, with each facility requiring its own
transmission connection. However, as the country's capacity
increases, such a model is unsustainable. Germany is the only
European country with what is known as a "mesh" system, where power
flows across the system and comes ashore at integrated landing
points, minimizing the onshore impact. Both Sweden and Norway are looking
into this model though, Ortiz Garcia said.
Ed Birkett, head of energy and climate at Onward, a center-right
thinktank, tweeted: "Interestingly, this still looks like mainly a
"radial" design, with a few "mesh" elements. I can see why this
makes sense, as you can't just run a single massive cable from
Scotland to southern England."
AR4 underpins offshore wind buildout
Complementing the transmission plan was the release of the
results of the biggest round yet of the UK government's renewables
auction scheme—AR4. A total of 93 projects won support from the
government. The 10.8 GW of projects are equivalent to 14% of the
UK's current 75.8 GW of capacity.
Five offshore wind projects with a combined capacity of 6.994 GW
formed the largest segment of the auction, delivering the lowest
prices of £37.35/MWh ($44.61/MWh, 2012 prices). The previous low
for offshore wind was £39.65/MWh in 2019's AR3. The price per MWh
was almost 70% lower than that of the first allocation round in
2015, BEIS said.
Among the winning offshore wind bids was Orsted's Hornsea 3
project, the world's biggest offshore wind farm with a capacity of
2.852 GW. Other winning bids came from Red Rock Power, ESB,
Vattenfall, Iberdrola, Ocean Winds, and the Ignitis Group.
AR4 cements the UK's position as the European leader in offshore
wind, trade group WindEurope said in a statement.
The prices, said Claire Mack, chief executive of trade group
Scottish Renewables, "showed how competitive renewable energy can
be with the right government support," but she warned such prices
made it harder to invest in the UK supply chain, where prices are
generally higher than overseas, arguing that cost cannot be the
only factor when selecting successful projects.
CBI's Thackray added: "The results from the latest CfD auction
round are a vote of confidence in the UK's plans for the energy
transition. Amid huge volatility in global wholesale markets,
renewables are attracting investment at low prices that can boost
energy security and affordability for households and
businesses."
However, the UK's 50 GW by 2030 target is too optimistic, even
with the start it has already made, said Ortiz Garcia, citing the
three or four years required to obtain permitting, a shortage of
vessels, and supply chain issues as three of the key
impediments.
Not enough to meet goals?
Even with all this planning and support for offshore wind, the
UK is still not far enough along the path to meeting its net-zero
goals. The independent Climate Change Committee (CCC) said in a
Progress Report issued 29 June that the government had set
ambitious targets, but it found "scant evidence of delivery against
these headline targets so far."
In most areas, the likelihood of under-delivery is high, it
said, warning that "this is a high-wire approach to net-zero. For
the UK's climate lead to be effective, the world must have
confidence that we will keep our promises and that we have a clear
and effective program to achieve our commitments."
Deployment of renewable electricity is one of the UK's strongest
suits, but the government was failing badly when it came to energy
efficiency in homes plus agriculture and land use, it said.
As a result, the CCC called for contingency plans that could
include curbs on demand growth for flights, comprehensive reform of
planning legislation, fixes for the skills gap bottlenecks, and a
promised Future Homes Strategy.