Obtain the data you need to make the most informed decisions by accessing our extensive portfolio of information, analytics, and expertise. Sign in to the product or service center of your choice.
As many as 54 countries may have installed floating offshore
wind capacity by 2050, according to a study released 20 June by the
UK-based research center ORE Catapult. At the moment, only the UK,
Portugal, Norway, and China have any operational capacity at
all.
Analysis for the study carried out by consultancy OWC identified
22 markets in which there were floating offshore wind installation
opportunities in the near term, which it defined as 2022 through
2035, while a further 32 are longer-term options through 2050.
OWC's analysis found the top five global markets (in descending
order) in terms of readiness were the UK, Japan, France, South Korea, and Taiwan. Norway and the US are
ranked just outside the top five, followed closely by the world's
largest offshore wind market by capacity currently—China.
RenewableUK data released 21 July, meanwhile, indicates the UK has the
biggest pipeline of floating wind projects in the world at 32 GW.
Sweden is second at 25 GW, Taiwan third with 21 GW, Ireland and
South Korea are tied for fourth at 16 GW, it said.
Such pipelines of floating wind, bolstered by increasing policy
support, suggest at least 10 GW of capacity is on track to be
commissioned by the end of 2030, according to the ORE Catapult
study.
That's not a moment too soon, according to Ingrid Lomelde, vice
president sustainability, Aker Offshore Wind, as floating wind is
the sector that most urgently needs to be commercialized for
countries and companies to reach their climate targets.
While far behind its bottom-fixed counterpart at the moment,
floating wind has greater potential and capacity, according to
S&P Global Commodity Insights analysts. Europe alone has
approximately 4,000 GW of untapped potential, which is about 80% of
potential regional offshore wind resources, all in water depths in
excess of 60 meters, the analysts said in a May report.
Such extraordinary potential and the offshore wind targets being
set by countries around the globe are "a positive challenge" for
developers, Stephan Buller, head of offshore portfolio management
and floating offshore wind at Siemens Gamesa Renewable Energy, told
a 21 June roundtable.
The ramp up is already under way. While the onshore wind market
saw a dip in installations in 2021, its offshore counterpart had
its best ever year, according to
the Global Wind Energy Council (GWEC). But installation levels
across the board must hasten yet further, the trade body said.
A four-fold increase in the pace of the global wind fleet
buildout is now necessary to avoid a global average temperature
increase of more than 1.5 degrees Celsius compared with
pre-industrial levels, as the Paris Agreement seeks, GWEC said.
Floating wind's compound annual growth rate will lag the overall
figure for the offshore wind sector through 2026, but will jump at
the end of the current decade and into the 2030s, with figures for
individual nations and regions underpinned in many cases by some of
the multi-gigawatt projects announced in recent weeks.
Gigawatt-scale projects
Irish developer Simply Blue on 18 May unveiled plans for two
multi-gigawatt floating wind projects in Sweden. The 2-GW
Skidbladner project is set to be located 100 kilometers (km)
southeast of Sweden's capital city Stockholm and the 2.75-GW
Herkules project would be about 60 km southeast of the island of
Gotland, it said.
A little over a month later, the developer on 21 June announced plans for its second
offshore wind project in Northern Irish waters. The 1.3-GW Olympic
floating wind facility is more than twice the size of Nomadic
Offshore Wind, which was unveiled in March.
Simply Blue is also behind one of the next Scottish floating
wind projects expected to leave the drawing board—Scotland is
home to the first two operational floating wind facilities. The
100-MW Salamander joint venture with fixed-bottom pioneer Ørsted
and engineering company Subsea 7 is expected to lay some of the
commercial floating offshore groundwork before the larger projects
planned as part of the UK's ScotWind tender come online. Of
the 25 GW of potential ScotWind capacity awarded, an estimated
15-17 GW is likely to be floating wind.
Across the North Sea, after being shut out of the ScotWind lease
sale, Norway's Equinor—which operates one of the two Scottish
floating wind facilities where turbines are currently
turning—has domestic gigawatt-scale ambitions.
On 17 June, Equinor said it was teaming up with
Petoro, TotalEnergies, Shell, and ConocoPhillips to study the
options for a 1-GW floating wind farm near the Troll and Oseberg
oil and natural gas fields. The partners are eyeing a 2027 startup
and the Trollvind facility would provide much of the electricity
needed to run the fields. An investment decision is set to be made
in 2023, Equinor said.
Floating wind is a "Swiss Army Knife" for decarbonization,
Lomelde told the roundtable. At the same event, Hanne Wigum,
Equinor wind concepts leader, said Trollvind would serve multiple
purposes:
Decarbonization of the oil and gas industry;
Delivery of power to a high demand area; and,
Industrialization of floating wind.
Estimates indicate Trollvind can deliver power for less than NOK
1/kWh (10 cents/kWh), Equinor said. When solar power was scaling
up, its 2020 US utility-scale target was 6 cents/kWh. Such a price
for Trollvind's power would ensure greater long-term access to
power at a stable price in the Bergen area, where Equinor said the
power situation is strained.
A day before the Trollvind announcement, Equinor said 16 June it
was teaming up with Technip Energies to develop floating wind steel
semi substructures it hopes will enable cost reductions. Equinor
said that "even though costs have come down substantially, there is
still a way to go for the floating technology to reach
commerciality."
Between Equinor's first floating turbine, Hywind Demo, and
world's first floating wind farm, Hywind Scotland, the cost per
megawatt fell 70% and it believes the 88-MW Hywind Tampen, located
in its home waters, will see costs decline a further 40%.
Norwegian Prime Minister Jonas Gahr Støre visited the NOK
5-billion Hywind Tampen's construction site on 7 June. Four of the
11 turbines have now been installed, Equinor said. Norway's
government wants offshore wind to produce as much electricity as
Norway currently produces and is planning to build 30 GW of
offshore wind by 2040.
Coming Spanish armada?
While Equinor was shut out in the pricey ScotWind auction,
Scotland's biggest utility, ScottishPower, was not. ScottishPower
is a subsidiary of Iberdrola, which plans to build up to 2 GW of
floating wind capacity in the waters of its native land. Spain
ranked 12th in the ORE Catapult readiness table.
Iberdrola isn't the only developer with floating wind goals in
Spain, the majority of whose coastal waters are too deep for
bottom-fixed turbines. On 17 June, Capital Energy and BlueFloat
Energy announced plans for the 50-MW,
€120-million ($126-million) Granadilla facility.
In addition, Simply Blue on 4 May signed a floating wind memorandum of understanding
with Proes Consultores and FF New Energy Venture that could see
more than 2 GW of capacity built in Spanish and Portuguese
waters.
Spain is an "attractive market for the development of floating
offshore wind due to the outstanding wind resource, the
longstanding coastal engineering and civil works heritage, as well
as superb supply chain capabilities," the three partners said.
Just over a month later on 6 June, Saitec Offshore Technologies
said it planned to develop a
50-MW floating wind facility off the coast of Catalonia by 2025.
The offshore turbines will use the company's SATH technology, which
is about to be tested in the Bay of Biscay.
Saitec's SATH demonstration work over the next two years in the
Bay of Biscay ahead of Mediterranean Sea deployment is part of the
ongoing development of designs for the nascent floating wind
sector. There has been no standardization of turbine or mooring
design yet, with some developers departing from the three-blade
option that dominates the onshore and bottom-fixed offshore wind
arenas.
Siemens Gamesa's Buller argued at the roundtable that developers
and OEMs must leverage their bottom-fixed turbine experiences and
adapt what the parties have already learned. The best plan, he
said, was to change as little as possible from bottom-fixed
development.
Conversely, Gunnar Herzig, World Forum Offshore Wind co-founder,
told the event "no-one quite knows" what the optimal number of
designs is. Innovation will be followed by standardization, Herzig
said, adding that commercialization will take place in the "not too
distant future."
Aside from the difference in designs, especially below the
surface of the water, one of the biggest areas of change from
bottom-fixed offshore wind will be a longer lead time in picking
the home port, Rick Campbell, UK-based consultancy Natural Power's
head of offshore markets, told roundtable attendees. Most floating
wind turbines are likely to be assembled port-side rather than out
on the water, he added.
Buller agrees. One of the key challenges for floating wind is
installation rates, he said. Developers must minimize the amount of
loading and manufacturing space used at ports and the time of
storage, he said. Equally, once the turbine is up and running, the
industry has to find a solution to carrying out equipment fixes at
sea and avoiding having to tow turbines back to port, he said.
This article was published by S&P Global Commodity Insights and not by S&P Global Ratings, which is a separately managed division of S&P Global.